Saturday, April 30, 2011

Basement Cinder Block Wall

Day 0: Oil tank from original heating system

Day 1: With oil tank removed, 90+ years old cinder block wall

Day 2: Scraped down all mold and mineral deposit build up from moist

Day 3: Patched with hydraulic cement on loose mortar cracks and holes


Day 4: 1st layer of Drylok painted

Day 5: 2nd layer, form board insulation

 Day 6: 2x4 and 1x3 studs nailed, mold resistance drywall installed



Day 7: Ceiling and access hole fabricated



Day 8: sheet rock joint compound, painted base coat


Day 9: Finished with Ocean Blue